Brazil auctions transmission lines to whoever asks the least annual revenue

ANEEL's December 2021 auction sold five 30-year grid concessions to lowest annual-revenue bidders — an average 50% discount, saving consumers ~R$5bn.

Agência Nacional de Energia Elétrica (ANEEL) · Taesa · Sterlite Power · Neoenergia · Energisa

The solution

Brazil needs continuous transmission expansion, and ANEEL has run a steady program of concession auctions. In the December 2021 auction, five lots covering 902 km of lines, three new substations and 750 MVA of transformation capacity were offered with 30-year concessions and required investment of about R$2.9 billion.

Winners were the bidders offering the lowest Annual Permitted Revenue (RAP) — the amount transmission companies may charge users each year. The five winning bids totalled R$202.5 million in annual revenue, an average discount of about 50% versus the reference values; winning discounts ranged from 27.83% to 66.09%.

ANEEL estimated the discounts would save consumers about R$5 billion, avoiding roughly a 3% tariff impact over coming years. The auction was the 19th in the electricity sector in three years, a period in which Brazil contracted around R$60 billion in electricity investments and expanded generation 16% and transmission 17%.

Why it worked

  • Lowest-revenue bidding forces companies to reveal true cost.
  • Fixed scope and term kept quality and deadlines enforceable.
  • Consumer tariffs fell by the full auction discount.
  • A steady pipeline of auctions kept competition alive.
What it achievedAuction the annual revenue, not the priceneat

What can be applied

When the asset is fully specified, bid on the revenue stream instead of negotiating tariffs: competing on annual revenue makes the grid build itself at the lowest regulated cost.

Aftermath

The December 2021 round was part of a program that contracted about R$60 billion in electricity-sector investment over three years; winners like Taesa, Sterlite, Neoenergia and Energisa took on construction, operation and maintenance of the new lines and substations.