The solution
Tocantins had a sparse population, long rural distances and roads that could become unreliable when creeks and crossings failed. A conventional road program might have ranked works mainly by engineering lists and traffic volumes.
PDRIS kept the asset-management discipline of CREMA contracts for 2,200 km of paved roads, but used an unusually grounded method for unpaved access. Community consultations were considered alongside traffic volumes to select more than 1,600 critical spots for bridges, culverts and drainage works.
From 2012 to 2021 the project gave 400,000 people all-season access to quality roads, reaching 100% of the rural population in western Tocantins. It also rehabilitated 5,500 km of unpaved roads through those critical-spot interventions.
The same package linked roads to practical regional development: at least 150 formerly subsistence small producers were enabled to sell crops in the market, and the environmental agency cut its licensing time to 36 days from 100.
What it achieved
Ask users where roads actually break
Why it worked
Community input exposed bottlenecks that network averages can hide.
Fixing crossings can unlock an entire route without rebuilding every kilometer.
CREMA contracts kept the paved network from slipping while rural access improved.
Bundling roads with agency capacity made access gains easier to preserve.
What can be applied
For rural networks, the highest-value road job may be a tiny failure point that only daily users can rank correctly.
Aftermath
The World Bank provided US$282 million for PDRIS, implemented by Tocantins agencies under Seplan leadership. After closure, the Bank described continued support for Tocantins' regional development agenda, including connectivity to rail corridors, road maintenance under climate stress and environmental monitoring tools.