The solution
Pennsylvania had thousands of structurally deficient bridges, but many were small rural spans that looked inefficient as one-off projects. PennDOT screened about 2,000 bridges and chose 558 with similar size, design, and permitting profiles, turning a repair backlog into one large, repeatable procurement.
The state awarded a DBFM concession to Plenary Walsh Keystone Partners. The private partner financed, demolished, rebuilt, and then maintained the bridges for 25 years, while PennDOT kept ownership and paid milestone and availability payments tied to usable bridges.
FHWA later listed the design-build contract at $899 million and total project cost at $1.118 billion. It said the approach was expected to save about 20% over the concession life versus PennDOT replacing and maintaining the bridges itself, with all 558 completed by the end of 2020.
What it achieved
Bundle tiny jobs until they become one investable product
Why it worked
Small bridges became financeable because the bundle was large enough for a specialist concessionaire.
Similar designs let the builder repeat parts, permits, crews, and methods instead of relearning each project.
Availability payments shifted attention from lowest construction bid to whether the bridges stayed usable for decades.
What can be applied
When work is too small to attract capital or industrial learning, standardize it, bundle it, and pay for service availability instead of isolated construction tasks.
Aftermath
The program became a U.S. reference case for bundling public infrastructure. FHWA highlighted it as Pennsylvania's first P3 project, the largest PAB financing for a P3 at the time, and a model for replacing many low-volume bridges faster than a traditional project-by-project cycle.